Hi @PatrickMcGarry1 ,
See attached xlsf with a sample on how to achieve that (sample is for 7 days).
First you need to get the number of days as an integer. You can set this up in your choices or create another hidden field, let’s call it number_of_days to return an integer by using an if statement, for example if(selected(${priority_code},"P1 - 24HRS", 1, if(selected(${priority_code},"P2 – 1WEEK",7, etc.).
Now that you have the days you can create a calculate field and calculate it as
date(decimal-date-time(today()) +int(${number_of_days}))
or
date(decimal-date-time(now()) +int(${number_of_days}))
Then put a constraint on your completion date field forcing it to be equal or bigger than the calculated field.
Hope this helps,
Uri
If this answer solved your question or if you found it helpful please mark it accordingly to help others who have the same question.